LAND WELL CLEANOUT COST COMPARISON
The following is a job comparison for a typical onshore well cleanout in Louisiana, using 1.25-inch coiled tubing and pressurized nitrogen. The example is for illustrative purposes only; actual savings may be more or less depending on well location and job specifications.
 
   
Costs WISE Unit Conventional Spread
Transportation 1 truck 4 trucks
Rig up time 1 hour 1 day
Job duration 1 day 1 day
Crew size 3 people 6 people
Rig down time 1 hour 1 day
     
Time saved 2 days  
Cost saved Approximately 30%  
 
 

 

 

 
 
Contents of this site are copyright 2006–2008 by WISE Well Intervention Services, Inc. All rights reserved.